Daimler Buses Italia and Italian charging infrastructure provider STI have secured a €28.04 million contract to supply 40 electric city buses and develop depot charging facilities for regional transport operator TUA Abruzzo in Italy.
The contract was officially awarded on 11 November 2026, following a tender launched in September 2025. It also includes an option for eight additional buses and responsibility for planning, building and maintaining the charging and power supply infrastructure at TUA’s depot on Via Aterno in Pescara.
Two Bus Sizes and Dedicated Charging Facilities
The order comprises 18 low-floor urban buses with a maximum length of 11 metres and 22 Class I vehicles measuring up to 12.48 metres. The specific Daimler models have not yet been announced.
The €28.04 million contract is approximately €3.92 million below the original estimated value of €31.97 million. Funding comes from the European Regional Development Fund, allocated through the Abruzzo region, and Italy’s National Strategic Plan for Sustainable Mobility.
Battery capacity and driving range were key factors in the tender evaluation. The buses are expected to complete full daily operating shifts without intermediate charging, allowing TUA to replace existing diesel vehicles on a one-for-one basis.
The depot project includes solar canopies covering 24 parking spaces, with photovoltaic panels and charging equipment. Its electrical infrastructure will be designed with additional capacity to accommodate future fleet expansion without major modifications.
Pescara Targets Diesel-Free Urban Operations
The arrival of the 40 buses will increase Pescara’s electric bus fleet to 60 vehicles. Around 90 buses currently operate on scheduled urban services each day, excluding reserve vehicles and trolleybuses.
TUA President Gabriele De Angelis said:
This investment underscores TUA’s commitment to the continuous renewal of its fleet, made possible by the funds provided by the Abruzzo region and the city of Pescara.
He added:
From 2027, we aim to operate urban transport in Pescara without diesel buses, primarily using electric buses and, to a lesser extent, natural gas buses. This is an important step towards a more modern, efficient, and sustainable public transport system for citizens.
Infrastructure and Deliveries Scheduled for 2027
Project planning is expected to be completed within 45 days, followed by technical inspections and an estimated 180-day construction period. The charging facilities are scheduled to become operational between April and May 2027.
The first bus deliveries are expected between June and July 2027. The additional charging capacity planned at the depot will also provide scope for TUA to increase its electric fleet beyond the initial 40 vehicles.